Plot 42, Block C, DHA Phase 8, Lahore · 5 Marla
Current Stage
Stage 2 · Grey Structure
Project Timeline
Stage 1 · Foundation & Excavation
CompletedIndependent soil test, anti-termite pre-treatment, RCC foundation pour to engineer's drawing. 7-day wet curing and slump tests on every batch. Signed off by independent structural engineer.
Structural Sign-off Document
Uploaded: 15 Jan 2026
Stage 2 · Grey Structure
In ProgressPlinth beam, columns, load-bearing brickwork, block-work and slab pours. Reinforcement strictly as per structural drawings. Cube tests at every 50 m³ of concrete.
Structural Sign-off Document
Pending slab pour — Aug 2026
Stage 3 · Interior Design & Finishing
UpcomingMEP, plaster, flooring, kitchen & wardrobes, paint, fixtures. Designed by the Sutoon Lahore studio; sourced against transparent bills of quantity.
Stage 4 · Handover & Possession
UpcomingSnagging walk-through, third-party inspection, as-built dossier handover and 12-month defect liability period.